Clarification on Closure Packet Revision Submittals

The RR Program would like to clarify that when submitting revisions to a closure submittal as requested by the DNR project manager, the consultant need only submit the revised pages (both paper and electronic copies) to the DNR project manager and the regional email box. This will save both the consultant and DNR project manager time in reviewing only the necessary information. In order to ensure that revisions are properly tracked, consultants are asked to initial and date all pages of any revisions submitted. Guidance for Submitting Documents (RR-690) was updated to reflect this clarification (Case Closure Submittals #6 on page 3).

(Visited 278 times, 1 visits today)